Owner Builder Certificate of Consent Victoria 2026: How to Apply

Writer: Owner Builder Institute
Owner Builder Institute
Nov 8
10 min read
Owner Builder Certificate of Consent Victoria 2026 guide featuring a construction site, application checklist and VBA360 portal

Planning to build, renovate or extend your own home in Victoria? If you're taking responsibility for managing the building work yourself, you may need an Owner-Builder Certificate of Consent before your project can proceed.


Sometimes called an owner builder permit Victoria or owner builder licence Victoria, the official term is Owner-Builder Certificate of Consent, issued by the Building and Plumbing Commission (BPC).


But who needs one? What documents are required? How much does it cost? And how do you apply through VBA360?


At Owner Builder Institute (OBI), we believe understanding the process before applying can help prevent unnecessary expenses, missing documents and avoidable delays.

This guide covers Victoria's current owner-builder requirements, including the $20,000 threshold, application documents, government fees and step-by-step application process.


What Is an Owner-Builder Certificate of Consent in Victoria?

An Owner-Builder Certificate of Consent is an approval issued by the BPC that allows an eligible property owner to undertake qualifying domestic building work as an owner-builder.


Rather than engaging a registered builder to manage the entire project, an owner-builder takes responsibility for managing or supervising building work on their own property.


This brings significant responsibilities, including:

  • Ensuring the appropriate building permits are obtained

  • Managing or supervising building work

  • Understanding construction site safety obligations

  • Ensuring the work complies with building regulations

  • Coordinating contractors and required inspections

  • Understanding insurance and defect obligations


Important: A Certificate of Consent is not a building permit. You must still obtain any required planning and building approvals before commencing relevant work.


When Do You Need a Certificate of Consent in Victoria?

From 1 July 2026, a Certificate of Consent is generally required for eligible domestic building work valued at more than $20,000, including labour and materials.

Previously, the threshold was $16,000, so some older websites may still display outdated information.


The value is calculated based on what it would cost if a registered builder completed the work, including an appropriate value for your own labour.


What projects can qualify?

Eligible owner-builder projects may include:

  • Constructing a new home

  • Renovating or extending an existing dwelling

  • Building an eligible garage or carport

  • Constructing a shed ancillary to a dwelling

  • Building certain other eligible domestic structures


For sheds, garages and ancillary structures, the work must relate to a single domestic dwelling. A dwelling should already exist or be constructed as part of the same project. A standalone shed on vacant land does not automatically qualify.


Owner-builders cannot personally carry out certain work, including demolition, subfloor work such as re-stumping or re-blocking, or relocating a home. Such work must be undertaken by appropriately registered building practitioners.


Even where a Certificate of Consent is not required, a building permit or other approvals may still be necessary.



Who Can Apply to Become an Owner-Builder in Victoria?

Under Victoria's Building Act 1993, applicants must meet specific eligibility requirements.


Generally, you must:

  • Own the land or qualify through an eligible company or trust arrangement.

  • Be carrying out eligible work relating to a single domestic dwelling.

  • Live, or intend to live, in the dwelling, subject to certain exceptions.

  • Not be carrying on the business of building.

  • Successfully complete the BPC eLearning assessment.

  • Complete the required construction induction training.

  • Meet restrictions relating to previous owner-builder projects and insurance obligations.


Can You Be an Owner-Builder More Than Once?

Victoria generally restricts applicants from being issued with a building permit as an owner-builder for a different property within the previous five years.

Exceptions may apply, including further work on the same home, certain small second dwellings and special circumstances recognised by the BPC.

If you have previously acted as an owner-builder, confirm your eligibility before applying again.


What Documents Do You Need for a Victorian Owner-Builder Application?

Preparing the correct supporting documents is one of the most important parts of your application.


Requirements vary depending on how the land is owned and the building work being proposed.


1. Current Victorian Certificate of Title

You will need evidence of land ownership, such as a Certificate of Title or Registered Search Statement.


The BPC requires this document to have been produced within seven days of submitting your application.


Ordering your title search too early may mean it is no longer sufficiently current when you're ready to lodge.


A practical approach is to prepare your other application documents first, then obtain your title search close to submission.


Included in OBI's $149 VIC Owner Builder Package: A current Victorian Certificate of Title, ordered when you're ready to lodge.



2. Proof of Identity

You may need photographic identification, such as a driver's licence or passport.

Ensure your personal details are consistent across your identification, eLearning account and VBA360 application.


3. BPC eLearning Certificate of Completion Code

The main applicant must complete the official BPC owner-builder eLearning assessment.

After successfully completing the assessment, you'll receive a unique Certificate of Completion Code, which is required when applying through VBA360.


You do not generally need to purchase a separate private owner-builder course to complete this requirement.


4. White Card Evidence

The BPC requires owner-builders to complete construction induction training and provide evidence of their White Card.


Recognised interstate construction induction cards may also be accepted.


5. Co-Owner Statutory Declarations

If your property has more than one owner, the other owners must be included in the application as co-applicants where required.


Each co-owner may need to complete the BPC's prescribed statutory declaration.

The main applicant is generally the owner who will live in the dwelling, subject to the applicable eligibility rules.


6. Company and Trust Documents

Different ownership arrangements require additional evidence.

If the land is owned by a company or owners corporation:

  • An ASIC company extract dated within seven days of application submission

  • Required written authorisation from directors dated within 28 days of submission


If the land is owned by a trust:

  • A certified copy of the trust deed, including amendments, identifying the trust, trustee and beneficiaries, meeting the BPC's 28-day document requirement

  • Written authorisation from the trustee or trustees approving the application and building work, dated within 28 days of submission


Some projects may also require a site plan, floor plan, planning permit or other supporting information. VBA360 will prompt applicants for additional documents where applicable.



How to Apply for an Owner-Builder Certificate of Consent Through VBA360

Victorian owner-builder applications are submitted online through the BPC's VBA360 portal.


Follow these seven steps to prepare your application.


Step 1: Check Your Eligibility

Confirm that you meet the BPC's eligibility criteria and that your proposed building work qualifies for an owner-builder Certificate of Consent.


Check the project value, type of work, ownership arrangement and any restrictions from previous owner-builder projects.


Step 2: Complete the Official BPC eLearning Assessment

Access the BPC's study materials and complete the official online assessment.

Once successful, keep your Certificate of Completion Code for your application.

The official assessment is separate from optional private courses.


Step 3: Complete Construction Induction Training

Ensure you've completed the required White Card training and have the correct evidence available.


Step 4: Prepare Your Supporting Documents

Gather your identification, eLearning completion code, White Card evidence, current property ownership information and any required statutory declarations.


Remember that your Certificate of Title must satisfy the BPC's seven-day recency requirement.


Step 5: Create Your VBA360 Account

Register through the BPC's VBA360 portal.


Use the same relevant personal details as your eLearning account to prevent mismatches.


You can begin an application and save it as a draft while preparing the remaining information.


Step 6: Complete and Review Your Application

Enter the required applicant, ownership and proposed building work details.


Where do you find the description of building work?

The BPC explains that the description may be found on architectural or building design drawings.


If your drawings are not yet available, contact your building surveyor to help identify the appropriate description.


Check that the work description reflects what you're proposing to build.


Upload the supporting documents requested through VBA360 and review all information before submission.


Step 7: Submit Your Application and Pay the Fee

Once your application is complete, submit it through VBA360 and pay the required BPC fee.


You can then track its progress online and respond if further information is requested.


How Much Does an Owner-Builder Certificate of Consent Cost in Victoria?

As at November 2026, the BPC Certificate of Consent application fee is $242.40.

This fee is non-refundable, including where an application is unsuccessful.


However, the Certificate of Consent fee is only one potential expense involved in preparing an owner-builder project.

Expense

Cost or requirement

BPC Certificate of Consent

$242.40

Official BPC eLearning assessment

Check current BPC requirements

White Card training

Varies by provider

Victorian Certificate of Title

Included in OBI's $149 VIC Package

Building permit and building surveyor

Project-specific fees

Drafting and building design

Quoted for your project

Engineering and energy assessments

Quoted where required

Optional OBI application support package

$149

The OBI package does not include the government application fee, White Card training or professional building approval services.


For owner-builders working to a budget, understanding these expenses in advance can make financial planning much easier.


How Long Does a Victorian Owner-Builder Application Take?

The BPC advises that processing a complete Certificate of Consent application takes approximately 45 business days, provided all required information has been submitted.


Applications can take longer if additional documents or clarification are required.


You can track your application through VBA360.

How Can You Avoid Unnecessary Application Delays?

Before submitting, check that:


  • Your eligibility has been confirmed.

  • Your eLearning completion details match VBA360.

  • Your White Card evidence is ready.

  • Your title search meets the seven-day requirement.

  • Your co-owner declarations are completed where applicable.

  • Company or trust documents meet the relevant deadlines.

  • Your description of building work is accurate.

  • All requested documents are attached.


These checks cannot guarantee approval or faster processing, but they can reduce the likelihood of preventable omissions.


How Long Does a Certificate of Consent Last?

Under the BPC's current requirements, a Certificate of Consent is valid for 12 months from the date of issue, or, where a building permit has been obtained, until that building permit lapses.


What Happens After Your Certificate of Consent Is Approved?

Receiving your Certificate of Consent is an important milestone, but it does not automatically authorise construction to begin.


Depending on your project, the next stages may involve:

Building design and documentation: Preparing drawings, engineering specifications, energy assessments and any other required reports.

Planning and building permits: Obtaining the appropriate approvals before starting relevant work.

Building surveyor: Engaging a building surveyor to assess documentation and undertake or arrange mandatory building inspections.

Contractor coordination and site safety: Understanding your responsibilities when organising building work and engaging trades.

Inspections and completion: Ensuring work complies with approved plans, relevant regulations and the applicable inspection requirements.


Make Your Victorian Owner-Builder Application Easier to Organise

At Owner Builder Institute, we understand that many first-time owner-builders want a clear process without spending unnecessarily on services they don't need.


Our VIC Owner Builder Package – $149 brings together practical guidance, documents and owner-builder resources.


Your package includes:

  • Current Victorian Certificate of Title, ordered when you're ready to lodge

  • Start Here Roadmap

  • Eligibility and Supporting Documents Checklists

  • BPC eLearning & VBA360 Application Guide

  • Building Surveyor & Permit Guide

  • Final Inspection, Completion & Owner Obligations Guide

  • Asbestos Awareness and Silica Awareness courses (non-accredited)

  • Project Management e-Kit

  • Defects Prevention & Quality Control System

  • Final Inspection & Defect Register

  • SWMS + Site Safety Kit

  • Quote Review System

  • Access to the Owner Builder Network for professional service quote enquiries


Our aim is to help owner-builders understand what needs to happen, when documents are required and how the different stages fit together.


We're also developing a network of drafting, engineering, energy assessment, surveying and other professionals, with a focus on competitive pricing and practical services for owner-builders.



OBI is an independent education and application support provider. The package does not replace the official BPC assessment, White Card, Certificate of Consent or building permit. Professional services and government fees are separate.


Frequently Asked Questions


Can I start building before my Certificate of Consent is issued?

Where a Certificate of Consent is required, you must obtain it before undertaking the relevant owner-builder work.


The BPC warns that failing to obtain consent before starting may affect your eligibility for a Notice of Cover, which can become important if you later sell the property.


Do I Need a Certificate of Consent for a Kit or Prefabricated Home?

Transporting a prefabricated home to your property does not itself require a Certificate of Consent.


However, qualifying domestic building work carried out on-site after delivery may require consent if its value exceeds $20,000.


This can include site preparation, installation, assembly and associated structural work.

For the Certificate of Consent calculation, the BPC says the cost of the prefabricated home itself and transportation to the site must be excluded.


Can Two People Apply as Owner-Builders on the Same Property?

Where the property is jointly owned, the main applicant is generally the owner who will reside in the dwelling, and other owners must be listed as co-applicants.


The required co-owner statutory declarations must also be supplied.


Can I Apply Before My House Plans Are Finalised?

Depending on your project, you may be able to begin preparing your application before all drawings are finalised.


However, you must still provide an accurate description of the proposed building work.


The BPC advises that this description may be available on architectural or building design drawings. If you don't have drawings, contact your building surveyor.


Some projects require additional plans or documentation before the application can be completed.


Is a Certificate of Consent the Same as a Building Permit?

No.


A Certificate of Consent establishes your eligibility to act as an owner-builder for the approved work.


A building permit is a separate approval required for building work that must be authorised under Victorian building legislation.


What Happens If My Certificate of Consent Application Is Refused?

If the BPC refuses your application, it will provide its decision and reasons.

Applicants have the right to appeal the decision to the Victorian Civil and Administrative Tribunal (VCAT) within 60 days of the decision letter.


Ready to Apply for Your Victorian Owner-Builder Certificate of Consent?

Becoming an owner-builder involves more than completing an online assessment.

From checking eligibility and obtaining a current Certificate of Title to preparing your VBA360 application and organising building approvals, each step requires accurate information and preparation.


The better organised you are from the beginning, the easier it is to understand what comes next.


Owner Builder Institute's $149 VIC Package brings practical guides, checklists, application resources and a current title search together in one place.



About Owner Builder Institute

Owner Builder Institute is an Australian owner-builder education and support business providing online training, practical guides, checklists and application resources to help Australians navigate their owner-building journey.


Last reviewed: 8 November 2026. Government requirements and fees can change. Always refer to the Victorian Building and Plumbing Commission for current information. Owner Builder Institute is an independent provider and is not affiliated with or endorsed by the BPC.